Stage 5. How long?

From signing to keys

A white and a dark second home in a paddock at dusk
Checked 16 October 2026. Every fact below links to the page it was read from.■ Check your block

Across South East Queensland most second homes take three to eight months from the first call to the keys, and the build is the short part: for a modular home about six weeks on site when the checks, the reports and the building approval were done before the contract. The rest is paperwork, and a planning application is the one thing that turns months into a year. Queensland law sets a handful of clocks inside that: the builder gives a signed copy of the contract within five business days, the owner can withdraw within five business days of receiving it, the contract states the start and practical completion dates, a commencement notice follows within 10 business days of starting on site, and a Form 21 final inspection certificate closes it.

The stages, in order

StageTypical time in SEQWhat stretches it
First call and site check1 to 2 weeksGetting everyone on site at once
Block check: zone, overlays, setbacks, sewer, access1 to 3 weeksOverlays, easements, a sewer main in the way
Reports: soil, survey, BAL, energy, engineering2 to 6 weeksEngineering waits on soil and survey; bushfire mapping adds a BAL report
Building approval and plumbing permit2 to 6 weeks once documents are completeMissing information, a siting referral to council
Planning application, only if neededMonthsInformation requests, public notification
Contract and cooling-off1 to 2 weeksFinance approval
FootingsDays to 2 weeksRain, rock, reactive clay, slope
Factory buildA written dateThe maker's order book
Crane day1 dayWind, access, road permits
Connections, decks, finishing2 to 4 weeksUtility bookings, plumbing inspections
Final inspection and certificateAbout a weekOutstanding items

Those times are what installers see on secondary dwelling jobs across the region. The clocks below are the law's.

The clocks Queensland law sets

  • Five business days for the builder to give a signed copy of the contract with plans and specifications.
  • Five business days of cooling-off from receiving that copy; on a contract of $20,000 or more the clock starts only once the QBCC's consumer building guide has arrived too. Too short to arrange a loan, so finance comes first.
  • A start date and a practical completion date in any contract of $20,000 or more, or the way each will be set, and a commencement notice with both within 10 business days of starting on site.
  • Ten business days for the builder to claim an extension of time in writing from becoming aware of a delay, approved by the owner in writing.
  • Ten business days for the builder to pay the home warranty premium after signing, and before work starts.
  • Ten business days for council to decide a standard plumbing permit application.
  • Practical completion is the day the work is done to the contract and the law with only minor defects left, recorded on a defects document, and the certifier's Form 21 final inspection certificate signs off a class 1a home.

Where the months go

A job with no planning application and a maker with a slot can run: reports and approval in six to ten weeks, contract and cooling-off in two, footings in one, crane day, and six weeks on site. Three to four months. The same job with an overlay that triggers a planning application adds the council's months in front, and the same job with a lender who pays nothing until the home is on the block adds the time to find the factory stages from elsewhere. Approvals time by council and finance for a factory-built home cover the two.

What to do in which order

  1. Block check, then the decision on a planning application. Week one.
  2. Soil test and survey ordered the same week; everything else waits on them.
  3. Finance lined up while the reports run.
  4. Selections decided before the contract.
  5. Contract, cooling-off, then the factory slot and the footings booked together.
  6. Crane day, connections, final inspection, the Form 21 and the plumbing certificate with the keys. Handover and defects covers the walk-through.
Start the clock with the block.The free block check does week one in ten seconds, and the install request reaches builders who work in the area.

See it for your block

Questions people ask next

How long does a granny flat take from start to finish in Queensland?

Most jobs in South East Queensland run three to eight months from first call to keys. A modular home is about six weeks on site once the reports and the building approval are done; a planning application, where the block needs one, adds months in front.

How long is the cooling-off period on a building contract in Queensland?

Five business days from receiving the signed copy of the contract, which the builder must give within five business days of signing. On a contract of $20,000 or more the clock starts only once the QBCC consumer building guide has also arrived.

What is the Form 21?

The final inspection certificate a building certifier issues for a class 1a home, such as a granny flat, or a class 10 structure. With the plumbing compliance permit it is the paperwork that comes with the keys.