Stage 1. Can I?

Do I need council approval, or a building approval only?

A dark-clad second home at golden hour, the bed and kitchen inside
Checked 16 October 2026. Every fact below links to the page it was read from.■ Check your block

Every new second home in Queensland needs two approvals, and some need three. A building approval, from a building certifier, is always required: it checks the home against the National Construction Code and the Queensland Development Code, and the certifier inspects it and signs it off. A plumbing permit, from council, is always required too, because connecting a new dwelling is permit work. A planning approval, also called a development approval or DA, is the third, and it is needed only when the council's scheme makes the home assessable: over the size cap, under the minimum lot, in the wrong zone, or inside an overlay that asks for it. The Planning Act 2016 calls the first case accepted development and the second assessable development.

The three approvals

ApprovalWho issues itWhen it is neededWhat it checks
Building approval (BA)A building certifier, private or council, licensed by the QBCCAlways, for every new secondary dwelling and for any structure converted into oneStructure, fire, energy, siting, the engineering, the BAL and flood levels. Inspections at set stages and a final certificate
Plumbing permitCouncilAlways. A new dwelling's plumbing and drainage is permit workThe drainage design, the connection to sewer or an on-site system, inspections at set stages, a compliance permit at the end
Planning approval (DA)Council as assessment managerOnly when the planning scheme makes the home assessableThe scheme's codes: size, siting, character, flood, bushfire, parking, and anything the overlay asks for

Accepted or assessable: the Planning Act test

Section 44 of the Planning Act 2016 sets three categories of development: prohibited, assessable and accepted. Accepted development needs no development approval. Assessable development does, and section 45 splits that into code assessment, against the scheme's codes only, and impact assessment, which also weighs public submissions and anything else relevant. A council's planning scheme is the instrument that puts a secondary dwelling into one of those boxes, and in South East Queensland the usual position is this: inside the cap, the lot rules and the setbacks, and outside any overlay that says otherwise, a secondary dwelling is accepted development. The certifier still has to be satisfied it meets the code, and will ask for a planning check before issuing the BA.

Push one rule and it becomes code assessable: a 90 m² home where the cap is 80, a home 25 m from the house where the rule says 20, a lot under the minimum. Most of those applications are decided by council officers against the code, without public notification.

The order, in practice

  1. Check the block: zone, lot, cap, overlays. This is the step that tells you whether a DA is in play.
  2. If a DA is needed, lodge it first. A certifier cannot issue the building approval until the planning approval is in place and its conditions are known.
  3. Engage the certifier, with the maker's plans, the engineering, the soil test and the energy report. The certifier issues the BA.
  4. The plumber lodges the plumbing permit with council on the state's Form 1. Council inspects the drainage before it is covered.
  5. Build, with the certifier's inspections at footings and frame, then the final certificate.

Who the certifier is, and what the energy and bushfire rules ask, is set out in granny flat rules in Queensland, explained. What each approval costs is on the next page.

Which one does this block need?The free block check reads the zone, the lot, the cap and the overlays for one address, which is the information that decides whether a planning application is in play.

See it for your block

Questions people ask next

Do I always need council approval for a granny flat in Queensland?

No. Every new secondary dwelling needs a building approval from a certifier and a plumbing permit from council. A planning approval from council is only needed when the planning scheme makes the home assessable: over the cap, under the minimum lot, outside a housing zone, or inside an overlay that asks for one.

Who issues a building approval?

A building certifier licensed by the QBCC, either a private certifier or one employed by council. The owner or the builder engages them. They assess the plans, inspect at set stages and issue the final certificate.

What is the difference between code assessment and impact assessment?

Under section 45 of the Planning Act 2016, code assessment is carried out against the planning scheme's codes only. Impact assessment also considers public submissions and any other relevant matter. Most secondary dwelling applications that are needed at all are code assessable.